Architectural Projects

 

Salt Lake City Library

HHI Corporation was the Architectural Precast Concrete subcontractor to Big-D Corporation. HHI designed, furnished and installed 87,000 square feet of architectural precast concrete panels. HHI’s partner, PRETECSA, in Mexico City, Mexico, manufactured the precast panels in accordance with HHI’s design. The panels were shipped by HHI from the manufacturer to Salt Lake City (2,330 miles). In total HHI shipped 140 loads and almost 4 Million pounds a combined distance of 326,220 miles or 13.1 times around the World. HHI installed the panels with its own forces, successfully and safely erecting 2,120 panels on the project.

 
Aircraft Maintenance Project

This multi-phased project included the construction of a new 2-story 38,000 square foot Aircraft Maintenance Facility, construction of a new 5,000 square foot office building, remodel of 2 Aircraft Hangars, major remodel of existing Maintenance Building, and the demolition of 6 existing buildings. Work included all divisions and was phased to allow the Owner to move and relocate personnel at various times throughout the project.

Wyoming State Hospital

The Wyoming State Hospital, located in Evanston, included construction of a 37,000 square foot adult care facility for use by the Wyoming State Department of Health. Key features were: 20 Foot High Concrete Shear Wall; Metal Casework; Metal Roofing & Wall Panels with Conical Shapes; Extensive Mechanical and Electrical; Metal Stud Framing; Metal-Framed Skylights; Extensive Site Development; Structural Masonry with Brick Veneer ; Fluid-Applied Flooring; Structural Steel, Joists, and Deck; Interior Architectural Woodwork; and Wet Pipe Fire Sprinklers.

HHI encountered many problems throughout the construction of this project. After the project was well underway it was evident that there were major design, code and health department compliance deficiencies in the contract documents. Throughout construction of the facility HHI submitted many VECP’s and 127 RFI’s. HHI worked closely with the Owner and Architect to correct the deficiencies in an effort to bring the building into compliance. Mid-way through the project the owner required the Architect to remove his original project manager from the project due to design and contractual issues and problems. Despite the many problems with the plans and architect, HHI forged ahead and completed the project, even to the extent of creating a steel erection crew from scratch when the original subcontractor pulled out.

Hill Air Force Base AAFES Mall

This project included the Design-Build of a new 109,227 square foot Main Base Exchange Shopping Center. Work included all divisions. Facilities included Common Support (waiting area, break room, electrical/UPS rooms, mechanical rooms, etc.), Administrative Areas (secretary/receptionist, supervisor and managers’ offices, communications room, and restrooms/locker rooms), Warehouse Areas (merchandise racks, stairs and mezzanines, conveyor belt, truck loading dock equipment, shelving systems), Retail Shops, Food Court, Outdoor Sales Greenhouse, and a 53,098 square foot sales area which includes electronics, clothing, jewelry and housewares. Site Work included sidewalks, 8 ½ acres of parking, access roads, exterior lighting, landscaping and security access gates, and 25 acres of site development. HHI also performed a large amount of work the owner had planned to self-perform, and still finished ahead of schedule.

Hill Air Force Base Clinic Addition

The construction of a new 13,300 square foot medical clinic for use by Hill Air Force Base Flight Medicine, Pediatrics and Audio/Visual Medicine included: Structural Steel Framing, Exterior Precast Concrete Panels, Built-up Asphalt Roofing, Interior Metal Stud Walls, and High Quality Finishes.

The project was originally designed and expected to bid five years prior to actual bid date. During the five years the project was mothballed by the Government, medical technology and construction standards changed. Once the project was released for bid, the new standards were incorporated into the project after the contract was awarded. These changed standards resulted from a significant number of change orders and decreased cost and schedule impact, which was easier and more advantageous for the owner than correcting the design prior to bid.

The largest dollar value changes were comprised almost entirely of two specific changes:

  • A Value Engineering Change Proposal submitted by HHI’s Engineers that redesigned the concrete foundations and over-excavation of the building. This VECP was accepted by the U.S. Army Corps of Engineers and resulted in a significant cost savings to the Government.
  • The addition of new fiber optic communication lines to the scope of work. The original contract required a connection into a non-existing fiber optic system. Base Communications was unable to complete the installation work necessary for our work to continue. HHI completed the new fiber optic communication system for Base Communications with a minimum impact to the overall cost and schedule.
Bear River Bird Education Center

A new beautiful 30,000 square foot administration building and visitors center at Bear River Migratory Bird Refuge. Visitors enjoy a beautiful exhibit area, gift shop, 130 seat theater/auditorium, outdoor class area, and walkways accessing critical wetlands. The facility provides US Fish and Wildlife personnel with office space, storage areas, maintenance areas, break and locker rooms and state-of-the-art laboratory. Unique facility features include outstanding acoustical design and striking, high resolution exhibits.

Poisonous Plants Research Laboratory

The Poisonous Plants Lab project included the construction of 6 ancillary outbuildings for the use of testing the effects of poisonous plants on livestock, including surgical and laboratory facilities. Work included all divisions. The facility will be used for the testing, inspection, and analyzing of the effects poisonous plants have on livestock. The buildings include a surgery building, extraction building, greenhouse building, cow pen, soil pen, and scale buildings. The project includes demolition work, modification and upgrading of office and warehousing areas, the construction and installation of two large bridge cranes, and improvements to shop and work areas. All construction was performed with adjoining buildings maintaining their normal operations.